The TISAX Audit Process Step by Step
Preparation means being able to explain and demonstrate actual implementation. The following three sections describe a practical sequence; agree dates and documents with the provider. The TISAX checklist covers registration and the overall process.
Phase 1: Prepare the self-assessment and records
Provide the self-assessment and agreed records, such as security rules, risk assessments, responsibilities and operational evidence. Agree suitable transfer or inspection arrangements. This does not require a separate preliminary assessment; you do not have to commission an additional “pre-audit”.
Agree submission deadlines with the provider. Check references, document versions and contact availability beforehand, so questions do not turn into a search for records during the assessment.
Phase 2: Interviews and Inspection
The provider interviews the people responsible for the agreed topics and examines the self-assessment. AL2 focuses on plausibility; AL3 verifies implementation more comprehensively. Schedule subject-matter owners according to the agreed plan.
AL3 generally includes an on-site assessment, which may examine access, secure areas and how procedures operate in practice. Scope and duration follow the assessment plan; there is no universal half-day or one-day duration for every visit.
Phase 3: Results Report
The report records scope, evaluation and findings. Categories depend on how a gap affects management-system effectiveness or security. “Must = major, should = minor” is not a valid formula.
- Conform: Assessed requirements are met; the result can lead to regular labels.
- Minor non-conform: Limited findings need correction. An accepted corrective action plan can enable temporary labels.
- Major non-conform: Significant gaps need treatment; this result does not yet provide a temporary label.
Remote vs. On-Site: AL2 and AL3 Compared
| Aspect | AL2 | AL3 |
|---|---|---|
| Method | Plausibility of self-assessment and evidence | Comprehensive verification of implementation |
| Interview | Usually by web conference | Interviews and on-site assessment |
| Local conditions | On-site inspection can be agreed as needed | Generally assessed on site |
| Duration | Plan with provider against scope and objectives | Plan with provider against scope and objectives |
Avoid 5 audit preparation mistakes
Mistake 1: Documentation created just before the audit
A policy written just before the appointment does not demonstrate use. Collect operational results such as approvals, completed reviews or restoration tests. The point is demonstrable use over a suitable period, not a blanket three- or six-month age requirement for every document.
Mistake 2: Interview partners not prepared
Explain the sequence and topics to participants. They should be able to describe their actual work and find the relevant rules and records. Rehearsed answers that do not match practice are not useful preparation.
Mistake 3: Evidence not readily available
Match evidence to the claim: a backup log demonstrates a backup; a restore test shows whether recovery succeeded. Identify who can explain it and check accessibility. Kopexa can retain evidence alongside the relevant measure.
Mistake 4: Physical security underestimated (AL3)
In AL3 audits, the physical inspection often becomes a stumbling block: defective access systems, poorly maintained visitor logs, open server room doors, missing signage for security zones, or unsecured removable media. Conduct an internal walkthrough before the audit and critically review all physical security measures.
Mistake 5: Self-assessment too optimistic
Base the self-assessment on actual implementation. If evidence for level 3 is missing, investigate the gap first. An honest assessment enables timely action; an optimistic number does not improve the process.
Remediation for Deviations
Not every audit is passed on the first attempt. The auditor distinguishes between two types of deviations:
Major non-conformity: A significant gap may call management-system effectiveness into question or create a substantial security risk. Plan root-cause correction and, where needed, immediate compensating measures with the provider. Classification depends on the actual finding.
Minor non-conformity: A limited finding still needs correction. An accepted corrective action plan can enable temporary labels. Follow-up assessments must confirm resolution. The process must finish no later than nine months after the initial assessment’s closing meeting; otherwise a new initial assessment is required. Waiting until the three-year renewal is not sufficient.
Tips for Audit Day
- Arrange a coordinator and available subject-matter owners.
- Prepare a suitable meeting room or secure remote access.
- Answer questions using actual practice and relevant evidence.
- Discuss missing implementation openly and explain planned treatment.
- Record findings and agreed next steps.
The complete preparation checklist can be found in our TISAX Checklist . Information about costs and timeline is available on our Costs and Process page.
Enter the assessment with evidence you can find
A missing record should become visible before the appointment. Our TISAX page shows how Kopexa supports measures, evidence and internal review.
Sources and reference date
Reviewed on 13 November 2026 using the ENX participant handbook and ISA 6, including the transition to ISA 2027.